Yeronga Priority Development Area

Share on Facebook Share on Twitter Share on Linkedin Email this link

The Yeronga PDA Development Scheme was approved by the Queensland Government and came into effect on 9 August 2019.

Download Yeronga PDA Development Scheme

The proposed development scheme was publicly notified from 1 April to 17 May 2019. A submissions report assessing the submissions and any amendments to the proposed development scheme was prepared.

Download Yeronga PDA Submissions Report

The development scheme is the regulatory document that assists with planning, carrying out, promoting, coordinating and controlling land development within the PDA. The Yeronga Priority Development Area (PDA) was declared on 10 August 2018 and an interim land use plan (ILUP)

The Yeronga PDA Development Scheme was approved by the Queensland Government and came into effect on 9 August 2019.

Download Yeronga PDA Development Scheme

The proposed development scheme was publicly notified from 1 April to 17 May 2019. A submissions report assessing the submissions and any amendments to the proposed development scheme was prepared.

Download Yeronga PDA Submissions Report

The development scheme is the regulatory document that assists with planning, carrying out, promoting, coordinating and controlling land development within the PDA. The Yeronga Priority Development Area (PDA) was declared on 10 August 2018 and an interim land use plan (ILUP) given effect. The development scheme supersedes the Interim Land Use Plan that has been in place since declaration of the PDA.

Public notification completed

EDQ has publicly notified the draft Yeronga PDA Development Charges and Offset Plan (DCOP) .

The draft DCOP was open for public review and comment for 30 business days from Monday 14 March to 5:00 pm on Tuesday 26 April 2022. All interested parties, including the community, residents, landowners, developers and business operators were invited to view the draft DCOP and make a written submission to the Minister for Economic Development Queensland (MEDQ).

Written submissions will be reviewed by the MEDQ, and a submission report will be prepared and available on the Yeronga PDA web page in the second half of 2022.

Following the consideration of submissions, the MEDQ will decide what changes, if any, will be made to the draft DCOP prior to adoption.

If you have any questions, please check the Q&A tab below to see if your question is answered or post your question for a response.

To stay informed about the finalisation and adoption of the draft DCOP, please register on the Have Your Say page.

  • New community centre for Yeronga PDA

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    A development application for the construction of a new community centre in the Yeronga Priority Development Area (PDA) has been approved.

    The approved development application, lodged on 31 January 2022, delivers on a 2017 state government election commitment to provide a permanent home for the Yeronga Community Centre in the PDA.

    The centre will be home to Community Plus (operator of the Yeronga Community Centre), as well as community interest groups - Annerley Stephens History Group and All Gauge Model Railway Club. It will offer a place for the community to develop connections and gain easy access to valuable social and support services.

    Locals will see movement on the site from October 2022 when works are expected to start to create internal roads and lots. Construction of the centre is scheduled to begin in November 2022 and with an expected completion date of July 2023, subject to weather conditions.

    For further information relating to the development approval, please visit the link below and click on the “decided applications” search field and type in “DEV2022/1264.”

    https://www.statedevelopment.qld.gov.au/economic-development-qld/buying-and-developing-land/development-applications-and-assessment/current-applications-and-approvals

  • Master plan development application approved

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Assessment of the development application (DA) for the Parkside Yeronga master plan is complete. A decision to approve the application, lodged in September 2021, was formally granted on 3 May 2022.

    To view the DA approval, please visit https://www.statedevelopment.qld.gov.au/economic-development-qld/buying-and-developing-land/development-applications-and-assessment/current-applications-and-approvals, click on ‘decided applications’ and search for DEV2021/1221.

    The development application for the new Yeronga Community Centre, lodged in January 2022, is still being assessed.

  • Public notification of draft Yeronga PDA Development Charges and Offset Plan

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    A draft Yeronga PDA Development Charges and Offset Plan (DCOP) has been prepared to address the planning and funding of infrastructure required to service development in the Yeronga PDA.

    The draft DCOP is open for public review and comment for 30 business days from Monday 14 March to 5:00 pm on Tuesday 26 April 2022.

  • Assessment of the master plan development application

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Assessment of the development application (DA) for Preliminary Approval Material Change of Use (master plan) and Reconfiguring a Lot for Parkside Yeronga is ongoing.

    All matters raised and feedback received from the community during the 20-business day public notification period for the application have been reviewed and will be considered by Economic Development Queensland’s (EDQ) Development Assessment team in the assessment of the application. The decision on the master plan application is expected in the next couple of months.

    A Material Change of Use application for the new Yeronga Community Centre has been submitted to EDQ for assessment. The community centre application is under review, and a decision on the application is expected by the Minister for Economic Development Queensland (MEDQ) in the coming months.

  • Development application open for public notification

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Development application public notification - 17 November to 15 December 2021

    Economic Development Queensland (EDQ) is the landowner of the former Yeronga TAFE site, known as Parkside Yeronga. EDQ, as master developer, has lodged a development application for:

    • preliminary approval material change of use (master plan); and
    • development permit for reconfiguring a lot (eight future development lots, new roads and public open space).

    The development application will be publicly notified for 20 business days, until close of business, Friday 17 December 2021.

    The application and all associated documents can be viewed on EDQ’s current applications web page.

    To search for the development application please type in DEV2021/1221 in the “current applications” search field of the website.

    For an overview of the proposed development, please read our November project update. Or take a moment to review a project presentation delivered to the local primary and high schools, and the Yeronga Child Development Centre.

  • Master plan development application lodged

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Master plan development application lodged

    The master plan development application (DA) for the Parkside Yeronga urban renewal precinct has been lodged.

    The DA and supporting documents are available on EDQ’s Current applications and approvals web page, reference DEV2021/1221.

    The proposed master plan includes a permanent home for the Yeronga Community Centre and a new purpose-built Children’s Health Queensland services hub. Retirement living facility, custom designed townhomes, social and affordable units and over 5,000 square metres of open space areas are also proposed.

    The public will have an opportunity to have their say on the proposed master plan of the former Yeronga TAFE site in November 2021. Notification dates are yet to be confirmed.

    Read the latest construction update - September 2021.

  • Construction update - May 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    For the latest Yeronga PDA construction update, please see here.

  • Construction update - December 2019

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Works to demolish and remediate the former Yeronga TAFE site are now complete.

    The contractor will soon begin removing all equipment and machinery from the site. Traffic control and signage will be in place to advise of any truck movements and to assist road users and pedestrians to move safely around the site during this time.

    The site will then be hydro-mulched as a form of dust mitigation, which will be regularly monitored. Further hydro-mulch will be laid if required in the future.

    We thank you for your patience while these works were completed. Our next update will be in early 2020, once a developer is appointed to undertake construction of the new mixed use precinct.

    In the meantime, if you have any questions about this project, please contact us through the Have your Say website, or email edqengagement@dsdmip.qld.gov.au.

    We wish you all a Merry Christmas and a happy and safe New Year.

    Kind regards
    The Yeronga Project Team


  • Construction Update - October 2019

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Works to complete demolition of the former Yeronga TAFE site are continuing, with ENERGEX advising EDQ they will begin disconnecting the existing transformer around Thursday 17 October 2019.

    Works to then demolish and remove the building will commence shortly after and will continue for approximately six weeks, weather and construction conditions permitting.

    These demolition and removal works will be undertaken in accordance with the relevant legislation and safety guidelines, as per all other demolition works previously undertaken on site.

    During these works, residents and businesses near the site may experience construction noise, dust, vibration and truck movements. Where necessary, traffic controllers and signage will be in place to assist with truck movements and to assist road users and pedestrians safely around the site.

    We appreciate your patience while these works are completed.

    If you have any questions in relation to these works, please contact us through the Have your Say website, or email edqengagement@dsdmip.qld.gov.au

    Kind regards
    The Yeronga Project Team


  • Construction update - September 2019

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Early works are continuing on the former Yeronga TAFE site, with EDQ’s contractors mobilising to begin removing a small number of trees from Monday 30 September 2019.

    These trees need to be removed as asbestos containing material has been found in their root systems. It should take approximately two days to complete, weather conditions permitting.

    Works will continue to remove asbestos containing material from site.

    Once these works are completed, ENERGEX will remove the transformer from the site, which will then enable demolition of the remaining building to be undertaken. This is likely to occur in late-2019.

    All vegetation and asbestos removal works are being undertaken in accordance with the relevant legislation and safety guidelines.

    During these works, residents and businesses near the site may experience construction noise, dust, vibration and truck movements. Where necessary, traffic controllers and signage will be in place to assist with truck movements and to assist road users and pedestrians safely around the site.

    If you have any questions in relation to these works, please contact us through the Have your Say website, or email edqengagement@dsdmip.qld.gov.au

    Kind regards
    The Yeronga Project Team