Category construction update   Show all

  • 3 July 2018 Northshore works Harbour Rd

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    BMD constructions, on behalf of EDQ, is upgrading the street lighting in a section of Harbour Road and Hercules Street. These works will create a more consistently lit street. Once installed, the new LED lighting will be more efficient and aesthetically pleasing including a reduction in the amount of overhead wiring.

    Where will it occur?

    View the map outlining the areas where pedestrian access will be affected during the upgrade. Please note access to properties will continue to be provided.

    When will this occur?

    Works are scheduled to commence on Monday 9 July 2018 between the standard council noise restriction hours of 6.30 am and 6.30 pm and will continue for approximately three weeks, weather permitting.

    What will I see and hear?

    The working areas will be separated with flagging and bollards, fencing will be used if required.

    There will be plant/equipment onsite including excavators, pole removal trucks, vacuum trucks, site vehicles, concrete trucks and general machinery.

    There will be noise from reverse squawkers and general machinery noises, with the occasional louder noise when cutting posts or hammering and cutting concrete. We will aim to keep the loud noises away from early morning as best we can.

  • 31 Jan 2018 Removal of on-street parking

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    On-street parking on Harbour Road will be removed from 5 am on Tuesday 23/01/2018—5 am 16/02/2018.

    BMD will be undertaking asphalt and surfacing works.

    Motorists are asked to please ensure all vehicles are removed from the kerbside prior to this date.

    Any cars parked in the area will be towed at the owners expense.

    Free alternative parking facility

    Free alternative parking is available in the secure parking facility on MacArthur Ave (adjacent to the pool tile company).

  • 30 Jan 2018 Night works notice

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    In order to continue works through the Macarthur Avenue/Remora Road/Hercules Street intersection, Hercules Street and Harbour Road it has become necessary to carry out a portion of the works at night. Night works will be undertaken on the 29th, 30th and 31st January 2018 (weather permitting). During these works we will have noise mitigation measures in place to reduce the impact to residents.

  • 20 Sep 2017 Update: Remora Rd, MacArthur Ave, Hercules St, Harbour Rd

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Updated information regarding upgrades to Remora Road, MacArthur Avenue, Hercules Street and Harbour Road.

    The works will involve upgrading key roads within Northshore from industrial access roads into roads that service Northshore Hamilton’s new uses as a residential, retail, commercial and recreational precinct.

    The road upgrades will provide:

    1. Additional traffic lanes with a median along Remora Road, Hercules Street and MacArthur Avenue allowing for future demand
    2. Dedicated cycle lanes linking Portside, a planned Riverwalk, and Kingsford Smith Drive.
    3. Resurfacing, some on street parking, new footpaths and landscaping to create tree lined boulevards along Remora Road, MacArthur Avenue, Hercules Street, Harbour Road
    4. New bus stops to improve public transport in the precinct
    5. A new connection road direct from Hercules Street to Kingsford Smith Drive
    6. Two new traffic lights on major intersections on MacArthur Avenue to improve safety for drivers, pedestrians & cyclists.

    Refer to the Project Update for full information (PDF, 814KB, updated 15/9/2017).

    How can I stay informed of roadwork program over the next 12 months?

    Residents and business owners will be regularly updated regarding specific timing for works and proposed traffic changes in their area via the website, email blasts and letterbox drops.

  • 15 June 2017 Infrastructure works update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Over the next 20 years, Northshore Hamilton will become home to 15,000 people, a workplace for 10,000 people and a waterfront recreational destination for thousands more.

    These essential roadworks are a part of a broader program of $33.5 million in infrastructure upgrades planned for the Northshore Hamilton Precinct over the next 2 years. Upgrades to amenity and safety include:

    • $2million to create a direct road link between Theodore Street and Barcham Streetwhich will reduce traffic pressure on Remora Road.
    • This $24million project to upgrade Remora Road, MacArthur Avenue, Hercules Street and Harbour Road, creating additional traffic lanes, a median strip, traffic lights, on street parking, new footpaths, dedicated cycle lanes, bus stops and extensive tree planting to create an appropriate streetscape for a residential, business and retail precinct.
    • $7.5 million to upgrade the park at Hercules Street, Remora Road and Kingsford Smith Drive. Works include increasing the park size from 1.5 to 2 hectares, upgrades to playgrounds, a new event space, and new water play.

    Residents, retailers and visitors may experience some impact on street parking, traffic delays, detours, construction noise and increased truck movements during the roadworks, however Economic Development Queensland will make every effort to keep disturbance to a minimum.

    To keep disruptions to a minimum, the contractor will work under a strict Construction Management Plan (CMP) which will include:

    • Permitted work hours
    • Noise and dust control
    • Traffic management plan.