Hercules Street Park construction update - May 2019

Construction completed since our last update

  • Completion of bulk earthworks
  • Finalisation of stormwater and sewer reticulation
  • Retaining wall construction
  • Soiling of Kingsford Smith Drive gardens
Construction sequence of works for the next four weeks
  • Construction of concrete foot paths
  • Installation of pathway lights
  • Installation of irrigation tank
  • Installation of trees
  • Commence amenities building ground works
  • Commence erecting picnic shelters